6. You have been assigned to a project where the objective is to create a new building. You are in charge of the demolition phase of this project, and you report to the project manager in charge of this project. You have been hired on contract and will be released at the completion of the demolition phase. What type of organizational structure you are working for?
A. Projectized organization
B. Weak matrix organization
C. Balanced matrix organization
D. Functional organization