47. Which of the following scheduling techniques incorporates a form of risk assessment?
A. Arrow Diagramming Method (ADM)
B. Program evaluation and Review Technique (PERT)
C. Precedence Diagramming Method (PDM)
D. Critical Path Method (CPM)