20. Which of the following is a common characteristic of most project life cycle descriptions?

A. Cost and staffing are low at the start, higher towards the end. and drop rapidly as the project nears completion.

B. The probability of successfully completing the project is highest at the start of the project.

C. Stakeholders have the most influence on the final characteristics of the product at the end of the project.

D. A and B