Menu PMI Prep Exam 8


3. Given the following estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days, what is the PERT weighted average?

A. 9

B. 4

C. 6.3

D. 6.1

Reset Clear Back Next