13. According to the PMBOK guide, the project statement of work(SOW) should contain or reference to all the following elements except ?

A. Business need, strategic plan, product scope description

B. Requirements, business need, stakeholder expectations

C. Strategic plan, product scope description, stakeholder influences, and business need

D. Project purpose, business case, stakeholder influences, product scope description