25. You are a project manager for Dutch Harbor Consulting. Your latest project involves the upgrade of an organization’s operating system on 236 servers. You performed this project under contract. You are in the Closing process and know that product verification is for what purpose?
A. To verify that all the work was completed correctly and satisfactorily
B. To evaluate project goals and ensure that the product of the project meets the requirements
C. To verify the goals of the project and ensure that the product of the project is complete
D. To evaluate all the work of the project and compare the results to project scope