Menu PMI Prep Exam 7


6. A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:

A. Change the project’s objectives

B. Call a meeting of the configuration control board

C. Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline

D. Change the scope baseline

E. Prepare a variance report

Reset Clear Back Next