16. A non-critical path activity is completed in half the time. Then:
A. All of the other alternatives apply.
B. The slack in the path containing this activity will increase.
C. The total cost for this activity has decreased.
D. The critical path is also reduced.
E. Manpower from this activity can be assigned to other activities.