32. Your team is split between two buildings on either side of town. As a result, the team isnt very cohesive because the members dont know each other very well. The team is still in the storming stage because of the separation issues. Which of the following should you consider?

A. Training

B. Co-location

C. Corrective action

D. Conflict resolution