Menu PMI Prep Exam 5


36. Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?

A. Applying calendars

B. Resource Leveling

C. Resource Planning

D. Resource Conflict Management

Reset Clear Back Next You did 50 of 50 questions(100%). of 50 were correct(0%).
b. Resource Leveling
Your message was sent.

1234567891011121314151617181920212223242526272829303132333435363738394041424344454647484950