22. Which of the following is an input to the Qualitative Risk Analysis process?

A. Risk register

B. Risk data quality assessment

C. Risk categorization

D. Risk urgency

Reset Clear Back Next You did 50 of 50 questions(100%). of 50 were correct(0%).
a. Risk register