11. Which of the following correctly explains the term “progressive elaboration”?

A. Changing project specifications continuously

B. Elaborate tracking of the project progress

C. Elaborate tracking of the project specifications with a change control system

D. Project specifications becoming more explicit and detailed as the project progresses