Menu PMI Prep Exam 4


5. You are managing a project that will implement a new Insurance software package. Two project team members have difficulty working together. They come to you, for help resolving the issues. You immediately set up a meeting that includes the functional manager. After the meeting you and the functional manager discuss the issues and agree on a solution. What type of organizational structure you are working in?

A. Functional

B. Balanced matrix

C. Projectized

D. Strong Matrix

Reset Clear Back Next