21. You are in process of identifying and documenting the project roles and responsibilities and create staffing management plan. All of the following should be addressed when listing the roles and responsibilities EXCEPT:

A. Competency

B. Authority

C. Responsibility

D. Compliance

Reset Clear Back Next You did 50 of 50 questions(100%). of 50 were correct(0%).
d. Compliance