Menu PMI Prep Exam 3


2. If a project with a SPI of 1.8, what you tell?

A. The project is running ahead of the schedule

B. The project is running behind of the schedule

C. Resources assigned to the project cost 1.8 units

D. None

Reset Clear Back Next