29. The project managers leadership style should be matched to the corresponding developmental level of the project team and should move through successive steps in the following order:
A. Disciplinary, autocratic, and participative
B. Staff planning, team training, and performance monitoring
C. Team building, team development, and responsibility assignment
D. Directing, coaching, supporting, and delegating