44. Project management processes can be organized into the following:

A. Initiating, planning, contracting, executing, and administration

B. Designing, developing, testing, and implementing

C. Initiating, designing, planning, executing, controlling, and implementation

D. Initiating, planning, executing, controlling, and closing