Menu PMI Prep Exam 1


17. If a project with a CPI of 0.8, what you tell?

A. The project is consuming more resources than anticipated.

B. The project is using fewer resources than anticipated.

C. The project is falling behind.

D. The project is running ahead of schedule.

Reset Clear Back Next