42. Decomposition is ___________.

A. What happens when changes to the project scope are ignore

B. Subdividing the major project deliverables into smaller, more manageable components

C. Defining a general product description into more discrete definitions of individual components

D. Subdividing the project into logical divisions of effort aligned within the performing organizations functional areas