46. A structured tool, usually industry or activity specific, used to verify that a set of required steps has been performed is called __________.

A. Quality Policy

B. check List

C. Trend Analysis

D. Paieto Diagram

Reset Clear Back Next You did 50 of 50 questions(100%). of 50 were correct(0%).
b. check List